TABLE A·I. Task I Preliminary Planning.
Program Milestone |
A |
B |
C |
|||||
Acquisition Phase |
Technology Development |
System Development and Demonstration |
Production and Deployment |
Operations and Support |
||||
Reviews and Audits |
SRR |
SDR(SFR) |
PDR |
CDR |
FRR(IFR) |
SVR |
PCA |
|
MECSIP TASK |
TASK I Preliminary Planning (5.1) |
|||||||
Program strategy (5.1.1) |
• Initial definition of: design objectives, identification of critical design failure modes, recommendations for materials selection and characterization, development testing, and manufacturing process controls |
• Matrix defined with milestones consistent with MECSIP Master Plan and IMP/IMS |
• Matrix updated |
• Matrix updated |
• Matrix updated |
• Matrix updated |
• Matrix updated |
|
Trade studies (5.1.2) |
• Initial assessment complete • Trade studies and Program impacts defined |
• Assessment revised to consider evolution of final mechanical system requirements |
• Trade studies updated |
• Assessment updated to reflect knowledge gained from detailed design |
• Assessment updated to reflect knowledge gained from test |
• Assessment updated to reflect knowledge gained from flight test |
||
Requirements development (5.1.3) |
• Concept for requirements management defined and coordinated |
• Specific approach and tool defined • Tool populated with initial requirements |
• Tool deployed and updated with latest requirements |
• Tool updated with latest requirements |
• Tool updated with latest requirements |
• Tool updated with latest requirements |
• Tool updated with latest requirements |
|
Preliminary integrity analysis (5.1.4) |
• Preliminary trade studies identified to determine the most cost-effective life requirements • Preliminary Integrity analysis for sizing, strength, durability, and damage tolerance estimates • Initial diagnostic capability estimates for critical items |
• Integrity analysis for sizing, strength, durability, and damage tolerance analysis for preliminary design completed |
• Integrity analysis for sizing, strength, durability, and damage tolerance analysis for preliminary design update |
• Integrity analysis of detailed design completed • Diagnostic capability Completed for critical items |
• Integrity Analysis reviewed to ensure SDF criteria has been met |